August 2021

As of August 05, 2021, the following works have been conducted:
– walls plastering inside the building;
– laying bricks to build partitions;
– making door apertures in the walls;
– laying of electric cables;
– repair works of the staircase (plastering);
– cleaning and plastering of walls and ceiling in the boiler room;
– installation of foundation for chimney stack; 