August 2020

Main works that have been conducted in August:

  • Installation of immobile working platforms for restoration works at the axes 1-8
  • Installation of the rolled material roof on the top of the meteo station 
  • Plastering inside the building
  • Heat insulation of the outside walls from the 2nd floor inside
  • Installation of the window blocks
  • Installation of the intermediate ceiling at the 1st floor
  • Restoration works at the front side of the observatory building
  • Integral waterproofing of the concrete and plastered walls with aqueuos solution